October 21, 2022-Paving Project on Sandy Hill Road to Begin on Tuesday, October 25, 2022

This is to inform you that on Tuesday, October 25, 2022 the paving project will commence on Sandy Hill Road.  Weather permitting the project will be completed on Friday, October 28, 2022.  

Tentative Schedule:

October 25-Milling
October 26-Sealing Cracks/Set Castings
October 27/28-Paving

During this time, alternate routes should be used.  Special accommodations will be made for Sandy Hill residents and school buses. 

Your regularly scheduled Garbage pickup will be uninterrupted; however, it will be collected between the hours of 5:30 am to 6:30 am.  Please plan accordingly.

If there are any changes to this schedule, we will update you.

Your cooperation during this period is greatly appreciated.