Update Paving Project on Cove Road-Thursday October 15, 2020
Below is the updated schedule from the Nassau County Public Works Department. Due to the expected heavy rain tomorrow, their schedule has been adjusted as follows:
Weather permitting, the schedule is as follows:
October 15-Thurs-Paving -Day 8 am to 5pm
October 15-Thurs- Complete Milling Down to South Street-Night 8pm to 5am
October 16-Friday- No Work Due to Weather
October 19-20 Mon & Tue-Complete Paving-Day 8am to 5pm
Striping will take place within a week after completion of paving, weather permitting.