Update Paving Project on Cove Road to Begin Tonight Tuesday, October 13th

We have been notified by the Nassau County Public Works Department that the paving project on  Cove  Road will begin tonight  on Tuesday , October 13th.  It is anticipated that this project will be completed on Friday or Monday  ( weather permitting).  Due to weather temperatures, the paving portion of the job will need to be done during the day instead of at night.  The milling on Tuesday and Wednesday will be done at night from  8pm to 5am.  The paving on Thursday and Friday (and possibly Monday) will  be done during the day from 8am to 5pm. 

Weather permitting, the schedule is as follows:

October 13- 14 Tues/Wed Milling of the Road & Sealing Cracks- Night 8pm to 5am
October 15-16 -Thurs/Fri-Paving -Day 8 am to 5pm
October  19-Mon- Complete Paving, if needed-Day 8am -5pm