Update Paving Project on Cove Road to Begin Tonight Tuesday, October 13th
We have been notified by the Nassau County Public Works Department that the paving project on Cove Road will begin tonight on Tuesday , October 13th. It is anticipated that this project will be completed on Friday or Monday ( weather permitting). Due to weather temperatures, the paving portion of the job will need to be done during the day instead of at night. The milling on Tuesday and Wednesday will be done at night from 8pm to 5am. The paving on Thursday and Friday (and possibly Monday) will be done during the day from 8am to 5pm.
Weather permitting, the schedule is as follows:
October 13- 14 Tues/Wed Milling of the Road & Sealing Cracks- Night 8pm to 5am
October 15-16 -Thurs/Fri-Paving -Day 8 am to 5pm
October 19-Mon- Complete Paving, if needed-Day 8am -5pm
We will continue to update you, if we receive any new information.